Büyükkışla Wind Power Plant
PowerKonnekt EMS and PPC for Entek Elektrik's 105 MW / 121 MWh storage-integrated solar power plant, with the first partial provisional acceptance completed in just 3 days.
Read case studyAnkara · Düsseldorf
Türkiye's First Storage Facility to Provide Frequency Control


Project Overview
Göktepe BESS is a 100 MW / 132 MWh battery energy storage facility in Yalova, Türkiye, owned by Polat Enerji and commissioned in 2026. It is one of the largest storage facilities in the country and a milestone for Türkiye's power system: it is the first facility in Türkiye to provide frequency control. iNOVAT delivered the facility's Power Plant Controller (PPC), Energy Management System (EMS) and commissioning, all built on its own software platform, PowerKonnekt.
A First for Türkiye's Grid
Göktepe BESS is the first facility in Türkiye to provide frequency control, made possible by PowerKonnekt. Frequency control is one of the most demanding services a power plant can deliver. The facility must sense deviations in grid frequency and respond within very short timeframes, accurately and reliably, every time. Battery storage is well suited to this role because of how fast it can respond. That speed only becomes a grid service when the control layer above the batteries can measure, decide and act in real time. PowerKonnekt provides that layer at Göktepe. It turns 100 MW of battery capacity into an active, responsive asset that helps keep Türkiye's grid stable. With this, battery storage in Türkiye moves beyond storing energy and starts actively supporting the stability of the national grid.
iNOVAT's Scope: PPC, EMS and Commissioning
iNOVAT was responsible for the control and management layer of the facility, along with its commissioning. As the Power Plant Controller, PowerKonnekt manages the facility at the grid connection point. It regulates active and reactive power and makes sure the plant meets grid code requirements and follows instructions from the system operator. As the Energy Management System, PowerKonnekt manages the battery side of the facility. It monitors state of charge and system health, distributes power commands across the plant and keeps every unit within safe operating limits. iNOVAT's commissioning team then took the facility through testing and validation, confirming that every function, including frequency control, performed as required before the plant entered operation.
Seamless Integration of Rolls-Royce and Siemens Equipment
Göktepe BESS brings together equipment from two global names, Rolls-Royce and Siemens. Coordinating a facility of this scale with equipment from different manufacturers requires a control platform that can speak to every component and manage them as one. iNOVAT integrated the Rolls-Royce and Siemens systems into PowerKonnekt through careful work on communication protocols, control logic, protection coordination and system-level testing. The result is a 100 MW facility that operates as a single, unified plant and responds to the grid as one asset rather than a collection of separate units.
Impact and Legacy
Göktepe BESS shows what battery storage can do for Türkiye's power system when it is paired with the right control technology. As the country's first facility to provide frequency control, it sets a reference for how future storage projects can support grid stability. This becomes more important as renewable energy takes a larger share of Türkiye's generation mix. For iNOVAT, the project shows that PowerKonnekt can manage utility-scale storage and deliver advanced grid services at national scale. It is a reference point for the large-scale projects ahead.


PowerKonnekt EMS and PPC for Entek Elektrik's 105 MW / 121 MWh storage-integrated solar power plant, with the first partial provisional acceptance completed in just 3 days.
Read case study
A pioneering storage installation for Osmangazi Elektrik Dağıtım within Türkiye’s first storage R&D project KEDEP